Answering: “Which of the following is NOT an essential component to initially achieving flow?”

Which of the following is NOT an essential component to initially achieving flow?
(choose the best answer)
A. Ensuring the Product Backlog is refined frequently.
B. Limiting Work in Progress (WIP).
C. Visualizing your workflow.
D. Actively managing WIP.
E. Inspecting & adapting your workflow.

Answering: “Which of the following is NOT an essential component to initially achieving flow?” Read More »

Answering: “A Scrum Team’s Definition of Workflow must have defined points at which the Scrum Team considers work to have started and to have finished. This allows the team to track their Work in Progress (WIP). How are these points defined?”

A Scrum Team’s Definition of Workflow must have defined points at which the Scrum Team considers work to have started and to have finished. This allows the team to track their Work in Progress (WIP). How are these points defined?
(choose the best answer)
A. Any refined Product Backlog item in the Product Backlog is WIP.
B. How it is defined and who defines it depends on the boundaries/scope of the Definition of Workflow.
C. In any way the Scrum Team chooses to define it. The Product Owner and the Developers must agree on the definition.
D. Any Product Backlog item in the Sprint Backlog is WIP.
E. In any way the Developers choose to define it. They have the final say on the Sprint Backlog.

Answering: “A Scrum Team’s Definition of Workflow must have defined points at which the Scrum Team considers work to have started and to have finished. This allows the team to track their Work in Progress (WIP). How are these points defined?” Read More »