Answering: “The Sprint is already underway. A Product Backlog item selected for the Sprint is unclear. What two things could the Developers do?”
The Sprint is already underway. A Product Backlog item selected for the Sprint is unclear. What two things could the Developers do?
(choose the best two answers)
A. With the Product Owner’s help, move the unclear work into a new Product Backlog item and place it on the Product Backlog.
B. Reach out to the Product Owner for the missing information before proceeding.
C. Make their best guess and proceed to avoid any delays.
D. Skip the item until the next Sprint.
E. Reach out to specialists in the product management department for the missing information.