Answering: “How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?”

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?
(choose the best answer)
A. A proportional amount of time on analysis, design, development, and testing.
B. As much as is required to meet the Scrum Team’s Definition of Done.
C. All development work and at least some testing.
D. As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.

Answering: “How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?” Read More »

Answering: “What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum Teams?”

What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum Teams?
(choose the best answer)
A. Create teams based on their skills across multiple layers (such as database, UI, etc).
B. Ask the Product Owner to assign the people to teams.
C. Ask the people to divide themselves into teams.

Answering: “What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum Teams?” Read More »

Answering: “Which are four attributes of a good bug report?”

Which are four attributes of a good bug report?
(choose the best four answers)
A. Expected results and observed results.
B. Includes code for a proposed fix.
C. Includes build or version number where the bug was found.
D. Explains some new system functionality desired.
E. Provides simple and repeatable reproduction steps.
F. Screenshots or other pictures of bug in action.

Answering: “Which are four attributes of a good bug report?” Read More »