Answering: “How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?”

How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?
A. 4 Iterations
B. 1 Iteration
C. 2 Iterations
D. 3 Iterations

Answering: “How many Iterations would it take for a team with a velocity of 20 story points per Iteration to finish a backlog of 60 story points?” Read More »

Answering: “During PI Planning, the Scrum of Scrums meetings helps accomplish which two actions?”

During PI Planning, the Scrum of Scrums meetings helps accomplish which two actions?

(choose the best two answers)
A. Exposing risks, impediments, and dependencies.
B. Comparing velocities across the teams.
C. Looking for ways to increase team velocity.
D. Rolling up the PI Business Value objectives.
E. Keeping the planning milestones on track.

Answering: “During PI Planning, the Scrum of Scrums meetings helps accomplish which two actions?” Read More »