Answering: “A Scrum Team is experiencing a growing list of impediments. Which techniques would be most helpful in this situation?”

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most helpful in this situation?
(choose the best two answers)
A. The Scrum Master discusses the impediments with the Scrum Team.
B. As a Scrum Team, prioritize the list and work on them in order.
C. Arranging a triage meeting with management.
D. The Product Owner should add the open impediments to the Product Backlog.

Answering: “A Scrum Team is experiencing a growing list of impediments. Which techniques would be most helpful in this situation?” Read More »

Answering: “What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply?”

What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply?
(choose the best two answers)
A. Use coaching techniques like open questions and active listening.
B. Ask an external agile coach what they recommend.
C. Involve the complete Scrum Team in making a decision.
D. Ask team members to take the issue up with the company’s Human Resources department.

Answering: “What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply?” Read More »

Answering: “You are the Scrum Master on a newly formed Scrum Team. Which two of the following activities would probably help the team in starting up?”

You are the Scrum Master on a newly formed Scrum Team. Which two of the following activities would probably help the team in starting up?
(choose the best two answers)
A. Ensure the team understands they need a Definition of Done.
B. Ensure the Scrum Team members have compatible personalities.
C. Have the manager for each Developer introduce their direct reports and go over their responsibilities on the Scrum Team.
D. Ask the Product Owner to discuss the product, its vision, history, goals, and context, as well as answer questions.
E. Introduce a bonus system for the top performers in the team.

Answering: “You are the Scrum Master on a newly formed Scrum Team. Which two of the following activities would probably help the team in starting up?” Read More »

Answering: “The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?”

The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?
(choose the best answer)
A. Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate Sprint.
B. Remind the Product Owner that their primary concern is the flow of value reflected in the ordering of the Product Backlog.
C. Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developers.

Answering: “The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?” Read More »

Answering: “During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?”

During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?
(choose the best answer)
A. The Product Owner and all stakeholders.
B. The Product Owner and the Developers.
C. The Developers.
D. The Scrum Master, the project manager and the Developers.

Answering: “During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?” Read More »