Answering: “The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?”

The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?
(choose the best two answers)
A. Coach the Product Owner in the values of Scrum and incremental delivery.
B. Bring up the problem in the Sprint Retrospective.
C. Nominate a proxy Product Owner.
D. Stop the Sprint, send the Product Owner to a course and restart.
E. Inform the Product Owner’s functional manager.

Answering: “The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?” Read More »

Answering: “The CEO asks the Developers to add a “very important” item to a Sprint that is in progress. What should the Developers do?”

The CEO asks the Developers to add a “very important” item to a Sprint that is in progress. What should the Developers do?
(choose the best answer)
A. Add the item to the current Sprint Backlog and begin work immediately since the request came from the CEO.
B. Add the item to the current Sprint and drop an item of equal size.
C. Add the item to the Sprint Backlog for the next Sprint.
D. Discuss the item with the other members of the Scrum Team so the team can decide what to do.
E. Add the item to the top of the Product Backlog.

Answering: “The CEO asks the Developers to add a “very important” item to a Sprint that is in progress. What should the Developers do?” Read More »

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here