Answering: “Which of the artifacts, from PI planning, highlights the new feature delivery dates, feature dependencies among teams and relevant Milestones?”

Which of the artifacts, from PI planning, highlights the new feature delivery dates, feature dependencies among teams and relevant Milestones?
A. Vision.
B. Program board.
C. Committed PI objectives.
D. PI plan document.

Answering: “Which of the artifacts, from PI planning, highlights the new feature delivery dates, feature dependencies among teams and relevant Milestones?” Read More »

Answering: “Which of the four fundamental team topologies is responsible for building and maintaining a part of the system that depends heavily on specialist knowledge?”

Which of the four fundamental team topologies is responsible for building and maintaining a part of the system that depends heavily on specialist knowledge?
A. Stream-Aligned teams.
B. Enabling teams.
C. Platform teams.
D. Complicated-Subsystem team.

Answering: “Which of the four fundamental team topologies is responsible for building and maintaining a part of the system that depends heavily on specialist knowledge?” Read More »