Answering: “The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?”
The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?
(choose the best answer)
A. The Developers. As a collective, they have a complete view of the work needed to transform Product Backlog items into Increments of product.
B. The PMO. They have all the history on projects delivered, and this enables the IT department to make delivery commitments.
C. The Product Owner. The Product Owner is required to commit on delivery to the users and the stakeholders.
