Hiro's approach goes beyond finding the right answer. The goal is to understand the principles behind it, see how the concepts apply in real situations and build the confidence to handle unfamiliar questions. Learners have credited Hiro's clear explanations and quick, personal answers with helping them pass demanding certification exams, from first-time foundational certifications to advanced professional levels.

Exam questions answered by Hiro

Each answer explains the reasoning behind the correct option, so you can apply it on the real exam.

Answering: “Which of the following activities will a Product Owner engage in during a Sprint?” (PSM I)

Which of the following activities will a Product Owner engage in during a Sprint?
(choose the best answer)
A. Answer questions from the Developers about items in the current Sprint.
B. Prioritize the Developers’ work on the Sprint Backlog.
C. Run the Daily Scrum.
D. Update management on what is being worked on.

Answering: “Which of the following activities will a Product Owner engage in during a Sprint?” (PSM I) Read More »

Answering: “Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Developers estimated as 90% done. The Developers, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.”

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Developers estimated as 90% done. The Developers, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
(choose the best answer)
A. The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected. It is the Scrum Master’s duty to assess whether repair is possible. or a restart with a more reliable team. If not, the Scrum Master should cancel the project.
B. The Developers make sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.
C. Replace the Scrum Master with a project manager, who takes control of the project.
D. The Developers should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.
E. The Developers inform Marian that the progress she has perceived to date is not correct. The Increment is not releasable. They give Marian their estimate of the effort it would take to get the past work “Done,” and suggest doing that work first before proceeding with new features. In the end, it is Marian’s call to continue the project or to cancel.
F. Add enough people to the Scrum Team for the deadline to be made.

Answering: “Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Developers estimated as 90% done. The Developers, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.” Read More »

Answering: “What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?” (PSM I)

What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?
(choose the best two answers)
A. By removing impediments that hinder the Scrum Team.
B. By facilitating Scrum Team decisions.
C. By starting and ending the meetings at the proper time.
D. By keeping high value features high in the Product Backlog.

Answering: “What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?” (PSM I) Read More »

Answering: “Which two of the following are true about the Scrum Master?” (PSM I)

Which two of the following are true about the Scrum Master?
(choose the best two answers)
A. The Scrum Master assigns tasks to Developers when they need work.
B. The Scrum Master helps those outside the team interact with the Scrum Team.
C. The Scrum Master teaches the Scrum Team to use timeboxes.
D. The Scrum Master is responsible for updating the Sprint Burndown.
E. At the Sprint Review, the Scrum Master identifies what work is done and not done.

Answering: “Which two of the following are true about the Scrum Master?” (PSM I) Read More »