Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.”

Select two ways in which leaving work undone at the end of the Sprint impacts transparency.
(choose the best two answers)
A. The lack of transparency leads to false assumptions about the current state of the product.
B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways.
C. When calculated and estimated, the total amount of undone work shows exactly how long until the Product Owner can release the Increment.
D. Undone work is acceptable as long as the Developers factor it into their future Sprint Plans.

Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.” Read More »

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?”

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
(choose the best answer)
A. The Developers pull work in agreement with the Product Owner.
B. The Scrum Teams choose the Weighted Shorted Job First.
C. The Product Owner should provide each team with its own Product Backlog.
D. The Scrum Team with the highest velocity pulls Product Backlog items first.
E. Each Scrum Team takes an equal number of items.

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?” Read More »