Answering: “True or False: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.”

True or False: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.
A. True
B. False

Answering: “True or False: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.” Read More »

Answering: “While changing software, you find a bug in a previously delivered piece of functionality. What should you do?”

While changing software, you find a bug in a previously delivered piece of functionality. What should you do?
(choose the best answer)
A. Fix the bug.
B. Stub out the code that caused the bug so it no longer occurs.
C. Revise the tests so that the bug no longer appears on the bug report.
D. Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product Backlog to be prioritized and fixed in an upcoming Sprint.

Answering: “While changing software, you find a bug in a previously delivered piece of functionality. What should you do?” Read More »

Answering: “Based on “Sprint 7 Burn-Down Chart” would you do anything different in Sprint 8?”

Based on “Sprint 7 Burn-Down Chart” would you do anything different in Sprint 8?
(choose the best two answers)
A. There is nothing wrong. The Developers will present all Product Backlog items selected for Sprint 7 at the end of the Sprint.
B. The Developers may forecast less overall work in Sprint 8.
C. Stakeholders will encourage the Scrum Team to estimate better during the Sprint 8 Planning Meeting.
D. The Developers re-estimate incomplete Product Backlog items and put them back into the Product Backlog for re-ordering. The Product Owner may ask the Developers to complete the unfinished Product Backlog items from Sprint 7 in Sprint 8.
E. The Scrum Master adds additional Developers for Sprint 8.
F. The Developers carryover incomplete Sprint Backlog items from Sprint 7 to Sprint 8 and monitor the Sprint 8 burn-down chart. As soon as deviation from trends is detected, the Developers work with the Product Owner to negotiate remaining work.

Answering: “Based on “Sprint 7 Burn-Down Chart” would you do anything different in Sprint 8?” Read More »