Answering: “While changing software, you find a bug delivered in a previous Increment. What should you do?”

While changing software, you find a bug delivered in a previous Increment. What should you do?
(choose the best answer)
A. Revise the tests so that the bug no longer appears on the bug report.
B. Talk to the Product Owner about what steps to take.
C. Set aside the Sprint Goal until the bug is fixed.
D. Stub out the code that caused the bug so it no longer occurs.

Answering: “While changing software, you find a bug delivered in a previous Increment. What should you do?” Read More »

Answering: “How much time is required after a Sprint to prepare for the next Sprint?”

How much time is required after a Sprint to prepare for the next Sprint?
(choose the best answer)
A. The break between Sprints is time-boxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
B. Enough time for the requirements for the next Sprint to be determined and documented.
C. Enough time for the Developers to finish the testing from the last Sprint.
D. None. A new Sprint starts immediately following the end of the previous Sprint.
E. All of the above are allowed depending on the situation.

Answering: “How much time is required after a Sprint to prepare for the next Sprint?” Read More »

Answering: “What are the top three benefits of a good Definition of Done?”

What are the top three benefits of a good Definition of Done?
(choose the best three answers)
A. A full description of all test steps.
B. Clear communication of the Scrum Team’s quality standards.
C. Guidance on the specific patterns to be implemented in code.
D. A fully valuable, useful Increment by the end of each Sprint.
E. An ongoing strategy or technique for steadily addressing technical debt.

Answering: “What are the top three benefits of a good Definition of Done?” Read More »