SAFe Scrum Master (SSM) exam question

Answering: “At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration effort, but they cannot integrate every Iteration and meet the planned scope. What should the Scrum Master suggest?”

By Hiro TakashimyaUpdated
Studying for the SAFe Scrum Master (SSM) exam? Try 10 free practice questions first.Start the free quiz →

At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration effort, but they cannot integrate every Iteration and meet the planned scope. What should the Scrum Master suggest?

This article unpacks a SAFe Scrum Master scenario and explains what makes the correct response effective.

Exam Question

At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration effort, but they cannot integrate every Iteration and meet the planned scope. What should the Scrum Master suggest?
A. Integrate the system during the IP Iteration.
B. Stop the Train and go back to waterfall until integration can occur.
C. Defer integration until the train is in the sustain and improve section of the Implementation Roadmap.
D. Discuss removing scope with Product Management to all for continuous integration.

Correct Answer

C

Explanation

Correct Answer

C. Defer integration until the train is in the sustain and improve section of the Implementation Roadmap.:
This aligns with the SAFe Scrum Master’s responsibilities and expected behaviors.

Incorrect Answers

A. Integrate the system during the IP Iteration.:
This is incorrect as it doesn’t reflect the SAFe Scrum Master’s duties or decision-making scope.

B. Stop the Train and go back to waterfall until integration can occur.:
This is incorrect as it doesn’t reflect the SAFe Scrum Master’s duties or decision-making scope.

D. Discuss removing scope with Product Management to all for continuous integration.:
This is incorrect as it doesn’t reflect the SAFe Scrum Master’s duties or decision-making scope.

Scrum Master Insights

  • Facilitation: Scrum Masters foster productive events and team alignment.
  • Coaching: They enable team-level agility through guidance and reflection.
  • Program Collaboration: Effective collaboration across ARTs ensures flow of value.

Relevance to the SSM Exam

This question represents key exam topics related to scaled Agile facilitation and team performance management in SAFe.

Key Takeaways

  • Scrum Masters play a crucial role in enabling Agile teams and events.
  • They promote alignment, remove impediments, and drive continuous improvement.
  • SAFe requires facilitation skills at both team and program levels.

Conclusion

Understanding these responsibilities equips you for real-world performance and the SSM certification exam.

Read more:

SAFe™ Scrum Master SSM Exam Prep

Get ready for the official SAFe Scrum Master (SSM) exam

207 SAFe Scrum Master (SSM) practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 45 random questions in 90 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official SSM exam is included with your SAFe course (retakes $50, paid to Scaled Agile).

More SAFe Scrum Master (SSM) exam questions

Practice all 207 SAFe Scrum Master (SSM) questions →

You cannot copy content of this page