The Developers determine how the work is done during the Sprint. No one outside them, including the Scrum Master or a manager, tells them how to turn Product Backlog items into an Increment.
Exam Question
Who determines how work is performed during the Sprint? (choose the best answer)
- A. The Scrum Master.
- B. The Scrum Team.
- C. The Developers.
- D. Subject matter experts.
- E. Team manager.
Correct Answer
C. The Developers.
Why This Is the Correct Answer
In the Scrum Guide, the Developers are accountable for creating the Sprint Backlog, the plan for the Sprint, and for adapting that plan each day toward the Sprint Goal. When describing Sprint Planning, the Guide says “no one else tells them how to turn Product Backlog items into Increments of value.” The Product Owner decides what is most valuable, and the Scrum Team as a whole agrees the Sprint Goal. But the how belongs to the people doing the work. They can ask experts or the Product Owner for help, but the decision on method stays with them.
Why the Other Options Are Wrong
A. The Scrum Master. The Scrum Master coaches and removes impediments. They do not direct how the work is done.
B. The Scrum Team. The whole Scrum Team agrees the Sprint Goal, but the Guide gives the how of the Sprint work specifically to the Developers.
D. Subject matter experts. Experts can give advice, but they do not decide how the Developers work.
E. Team manager. Scrum has no team manager role. Directing the work from outside breaks self-management.
Exam Tip
Separate the “what” from the “how”. The Product Owner leads on what, the Developers decide how, and the Scrum Team shares the Sprint Goal.
Key Takeaways
- Developers decide how to do the Sprint work.
- The Product Owner shapes what, not how.
- Outside experts advise but do not decide.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- When Developers are having trouble delivering an Increment because they do not understand a functional requirement, what should they do?
- Which do self-managing Developers choose?
- As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?” (PSM I)
- How should a Scrum Team deal with non-functional requirements?
- True or False: Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.” (PSM I)