The Daily Scrum, Sprint Review and Sprint Retrospective are feedback loops in Scrum. Release Planning is not a Scrum event, and refinement is an ongoing activity rather than an event.
Exam Question
Which three of the following are feedback loops in Scrum?
(choose the best three answers)
A. Daily Scrum.
B. Sprint Review.
C. Release Planning.
D. Sprint Retrospective.
E. Refinement Meeting.
Correct Answer
A, B and D.
Why This Is the Correct Answer
Scrum is built on empiricism, and the Scrum Guide describes each event as a formal opportunity to inspect and adapt Scrum artifacts. The Daily Scrum inspects progress toward the Sprint Goal every 24 hours and adapts the Sprint Backlog. The Sprint Review inspects the Increment with stakeholders and adapts the Product Backlog. The Sprint Retrospective inspects how the team worked and adapts its process and Definition of Done. These three create feedback at different levels: daily plan, product and team. Sprint Planning is also an event, but it is not listed here. Refinement is real work but has no fixed timebox or event structure.
Why the Other Options Are Wrong
C. Release Planning. Release Planning is not part of the 2020 Scrum Guide. Teams may plan releases, but it is not a Scrum event.
E. Refinement Meeting. Product Backlog refinement is an ongoing activity, not one of the five Scrum events.
Exam Tip
Know the five Scrum events: the Sprint, Sprint Planning, Daily Scrum, Sprint Review and Sprint Retrospective. Names like Release Planning or Refinement Meeting are not on the list.
Key Takeaways
- Scrum events are formal points to inspect and adapt.
- Daily Scrum, Sprint Review and Retrospective give feedback at different levels.
- Refinement is an activity, not an event.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- Which three of the following are timeboxed events in Scrum?” (PSPO I)
- True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.” (PSPO I)
- Who is accountable for tracking the remaining work toward the Sprint Goal?” (PSPO I)
- When is a Sprint over?” (PSPO I)
- Why is it important that there is only one Product Owner per product?” (PSPO I)