All of these are fair topics for a Sprint Retrospective. Communication, how the team plans, the skills the Developers need and the Definition of Done all affect quality and effectiveness.
Exam Question
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
(choose the best answer)
A. Methods of communication.
B. The way the Scrum Team does Sprint Planning.
C. Skills needed to improve the Developers ability to deliver.
D. The Definition of Done.
E. All of the above.
Correct Answer
E. All of the above.
Why This Is the Correct Answer
The Scrum Guide says the purpose of the Sprint Retrospective “is to plan ways to increase quality and effectiveness.” The team inspects how the last Sprint went “with regards to individuals, interactions, processes, tools, and their Definition of Done.” Methods of communication fall under interactions. The way the team runs Sprint Planning is a process. Skills the Developers need affect individuals and their ability to deliver. The Definition of Done is named explicitly. Anything that helps the Scrum Team work better is open for discussion.
Why the Other Options Are Wrong
A. Methods of communication. A valid topic, but not the only one.
B. The way the Scrum Team does Sprint Planning. A valid topic, but other options also apply.
C. Skills needed to improve the Developers’ ability to deliver. A valid topic, but not the full answer.
D. The Definition of Done. A valid topic named in the Scrum Guide, but the others apply too.
Exam Tip
The Sprint Retrospective covers individuals, interactions, processes, tools and the Definition of Done. If every option fits one of those, choose “All of the above.”
Key Takeaways
- The Sprint Retrospective looks at people, interactions, process and tools.
- The Definition of Done is an explicit retrospective topic.
- Anything that improves quality and effectiveness can be discussed.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- True or False: The Product Owner makes sure the right stakeholders are invited to the Sprint Retrospective. They might have important instructions for team improvements.” (PSM I)
- What is the Scrum Master responsible for during the Sprint Retrospective?
- A Sprint Retrospective should be held:
- Which are appropriate topics for discussion in a Sprint Retrospective?” (PSM I)
- When is it most appropriate for a Scrum Team to change the Definition of Done?” (PSM I)