Exam Question
When does a Sprint conclude?
(choose the best answer)
A. When all Product Backlog items meet their Definition of Done.
B. When the Sprint Retrospective is complete.
C. When the Product Owner decides enough has been delivered to meet the Sprint Goal.
D. When all the tasks are completed by the Developers.
Correct Answer
B. When the Sprint Retrospective is complete.
Explanation
Correct Answer
B. When the Sprint Retrospective is complete:
A Sprint officially concludes with the completion of the Sprint Retrospective. This event follows the Sprint Review and provides an opportunity for the Scrum Team to inspect and adapt their processes for the next Sprint.
Incorrect Answers
A. When all Product Backlog items meet their Definition of Done: The Sprint does not conclude based on the completion of Product Backlog items alone. It is a time-boxed event, and its conclusion is marked by the end

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- When must the Product Owner participate in the Daily Scrum?” (PSPO I)
- Who determines how many Product Backlog items the Developers select for a Sprint?” (PSPO I)
- True or False: Multiple Scrum Teams working on the same project must have the same Sprint start date.” (PSPO I)
- Who creates the Definition of Done?” (PSPO I)
- What is the accountability of the Product Owner during Sprint 0?” (PSPO I)