PSM I exam question
When does a Developer become accountable for an item in the Sprint Backlog

Answering: “When does a Developer become accountable for an item in the Sprint Backlog?” (PSM I)

By Hiro TakashimyaUpdated
Studying for the PSM I exam? Try 20 free practice questions first.Start the free quiz →

Accountability for Sprint Backlog Items in Scrum

Accountability within a Scrum Team is a key factor in ensuring the successful delivery of product increments. Here’s an analysis of an exam question related to when a Developer becomes accountable for an item in the Sprint Backlog:

Exam Question

When does a Developer become accountable for an item in the Sprint Backlog? (choose the best answer)

  • A. At the Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.
  • B. Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.
  • C. As soon as a Developer on the Scrum Team can accommodate more work.
  • D. During the Daily Scrum.

Correct Answer

B. Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.

Explanation

Why B is Correct

In Scrum, accountability for the Sprint Backlog items is shared among all Developers on the Scrum Team. This collective accountability ensures that the team works collaboratively and supports each other in completing the work. There is no individual assignment of tasks to Developers; instead, the team decides together how to accomplish the Sprint Goal and manage the workload.

Key Points about Shared Accountability:

  • Collaborative Work: Scrum promotes teamwork and collaboration, with all Developers sharing responsibility for delivering the Sprint Backlog items.
  • Flexibility: Shared accountability allows for greater flexibility, as team members can help each other and adjust their focus as needed to meet the Sprint Goal.
  • Self-Organization: The team self-organizes to determine how best to complete the work, without assigning specific tasks to individual Developers.

Examining the Other Options

A. At the Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers: This option contradicts the principle of shared accountability and self-organization in Scrum. Tasks are not split and assigned individually during Sprint Planning.

C. As soon as a Developer on the Scrum Team can accommodate more work: This option implies individual assignment of tasks, which is not in line with Scrum’s emphasis on collective responsibility.

D. During the Daily Scrum: The Daily Scrum is a time for the team to inspect progress and adapt their plan, but it does not involve assigning individual accountability for specific tasks.

Roles and Responsibilities in Scrum

  • Developers: Share accountability for completing the Sprint Backlog items and work collaboratively to achieve the Sprint Goal.
  • Scrum Master: Facilitates the Scrum process and ensures that the team adheres to Scrum principles, including shared accountability.
  • Product Owner: Prioritizes the Product Backlog and ensures that the team works on the most valuable items, but does not assign tasks to individual Developers.

Relevance to the PSM I Exam

Understanding the concept of shared accountability is crucial for the PSM I exam. This knowledge helps candidates recognize the importance of teamwork and collaboration in Scrum. Mastery of these concepts is essential for effectively implementing Scrum practices and achieving certification.

Conclusion

In Scrum, a Developer never becomes individually accountable for an item in the Sprint Backlog. Instead, all Developers on the Scrum Team share accountability for the Sprint Backlog items. This collective responsibility ensures that the team works together to deliver the product increment. Understanding this aspect of the Scrum framework is crucial for success in the PSM I exam.

Scrum Master PSM I™ Exam Prep

Get ready for the official PSM I exam

480 PSM I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.

More PSM I exam questions

Practice all 480 PSM I questions →

You cannot copy content of this page