Working with Multiple Scrum Teams on the Same Product
In Scrum, when multiple teams are working on the same product or system, the Product Backlog is a critical element that guides their work. The Product Backlog contains all the work needed for the product, ordered by the Product Owner based on value, risk, and other factors.
Exam Question
True or False: Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
A. True
B. False
Correct Answer
A. True
Explanation
Correct Answer
A. True:
In Scrum, when multiple Scrum Teams are working on the same product or system, they all select work from the same Product Backlog. The Product Backlog is a single, ordered list of everything that is known to be needed in the product. It is managed by the Product Owner, who is responsible for ordering the items to maximize the value delivered by the teams. Having a single Product Backlog ensures that all teams are aligned and working towards the same goals, preventing duplication of effort and conflicting priorities.
Key Points
- Single Product Backlog: There is only one Product Backlog for the entire product, regardless of the number of Scrum Teams working on it.
- Coordination Across Teams: This approach ensures that all teams are coordinated and that the most important work is being done first.
- Product Owner’s Role: The Product Owner is responsible for ordering the Product Backlog items to maximize value, which guides all Scrum Teams in selecting their work.
Relevance to the PSD Exam
Understanding how multiple Scrum Teams interact with the Product Backlog is essential for the PSD exam. It highlights the importance of a unified approach to product development, ensuring that all teams are aligned and focused on delivering value.
Key Takeaways
- Multiple Scrum Teams working on the same product or system select work from a single, shared Product Backlog.
- The Product Backlog is managed by the Product Owner, who orders the items based on value and other factors.
- This unified approach ensures coordination and alignment across all teams working on the product.
Conclusion
When multiple Scrum Teams are working on the same product, they all select their work from a single Product Backlog. This ensures alignment and focus on delivering the most valuable features or fixes. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.