False. Cross-functional teams have all the skills to deliver value across the whole system, not just one component or layer.
Exam Question
True or False: Cross-functional teams are optimized to work on one component or layer of a system only.
A. True
B. False
Correct Answer
B. False
Why This Is the Correct Answer
The Scrum Guide says Scrum Teams “are cross-functional, meaning the members have all the skills necessary to create value each Sprint.” Value usually requires changes across several layers, such as user interface, business logic and data. A team limited to one layer can only finish part of a feature and must hand off the rest, which creates delays and integration risk. Cross-functional teams are set up to deliver complete, usable slices of functionality instead.
Why the Other Options Are Wrong
A. True This describes a component team. Component teams depend on others to finish features, so they struggle to deliver a done, usable Increment on their own.
Exam Tip
Statements tying a Scrum Team to one layer or component are false. Cross-functional means able to deliver end-to-end value.
Key Takeaways
- Cross-functional teams deliver value across all layers.
- Component teams create hand-offs and integration risk.
- A usable Increment usually spans several parts of the system.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- Why does the Product Owner want the Scrum Team to adhere to its Definition of Done?
- Which of these may a Scrum Team deliver at the end of a Sprint?” (PSPO I)
- Which statement best describes Scrum?” (PSPO I)
- Developers are self-managing, which of the following do they manage?” (PSPO I)
- Who must attend the Daily Scrum?” (PSPO I)