Nexus Integration Team Accountability
In a Nexus, the Nexus Integration Team (NIT) plays a crucial role in ensuring that there is an Integrated Increment at the end of each Sprint. This responsibility aligns with the principles of Scrum, emphasizing transparency, inspection, and adaptation across all Scrum Teams involved in the Nexus.
Exam Question
True or False: A Nexus Integration Team is accountable for there being an Integrated Increment at the end of each Sprint.
A. True
B. False
Correct Answer
A. True
Explanation
Correct Answer
A. True:
The Nexus Integration Team is indeed accountable for ensuring that there is an Integrated Increment at the end of each Sprint. This accountability ensures that the combined efforts of all Scrum Teams result in a potentially shippable product increment. The NIT supports the teams by addressing dependencies, integrating work, and ensuring that integration issues are resolved promptly.
Role of the Nexus Integration Team
- Facilitating Integration: The NIT ensures that all work done by the Scrum Teams is integrated into a cohesive whole. They provide support and guidance on integration practices and tools.
- Ensuring Accountability: While the NIT does not do the integration work themselves, they ensure that all Scrum Teams adhere to the necessary integration practices to produce a Done Increment.
- Raising Transparency: The NIT helps make integration issues and dependencies visible to all teams, facilitating collaboration and resolution of these issues.
Relevance to the SPS Exam
Understanding the role and accountability of the Nexus Integration Team is critical for the SPS exam. It demonstrates the ability to manage and coordinate multiple Scrum Teams effectively, ensuring that they work together to produce a cohesive product increment.
Key Takeaways
- The Nexus Integration Team is accountable for ensuring an Integrated Increment at the end of each Sprint.
- They facilitate integration, ensure adherence to integration practices, and raise transparency.
- Understanding this role is vital for effectively managing large-scale Scrum projects.
Conclusion
The Nexus Integration Team’s accountability for the Integrated Increment ensures that multiple Scrum Teams work cohesively towards a common goal. This principle is fundamental to the success of large-scale Scrum implementations.

Get ready for the official SPS exam
182 SPS practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official SPS exam fee ($250) is paid separately to Scrum.org.
More SPS exam questions
- True or False: Multiple Scrum Teams working on the same project must have the same Sprint start date.” (SPS)
- True of False: There is one Product Backlog for a Nexus.
- You are working with multiple Scrum Teams that are working in the same code base. They suffer from coordination problems and mutual dependencies.” (SPS)
- True or False: All Scrum Team members must attend the Nexus Daily Scrum.
- True or False: A Nexus Integration Team is responsible for actually doing the integration work during the Sprint.