Understanding Self-Management in Scrum Teams
Self-management is a core principle in Scrum that empowers teams to make decisions about how they work. Self-managing Scrum Teams are accountable for all aspects of their work, including planning, execution, and delivery. Understanding the behaviors that exemplify self-management is critical for Scrum Masters and team members alike.
Exam Question
Describe two examples of behaviors that self-managing Scrum Teams exhibit.
Correct Answer
1. The Developers select their own work during the Sprint.
2. The Developers make decisions on how to achieve the Sprint Goal without needing external direction.
Explanation
Example 1: The Developers Select Their Own Work During the Sprint
In a self-managing Scrum Team, Developers are empowered to choose the work they will take on during the Sprint. This is evident in how they interact during Sprint Planning and throughout the Sprint:
- Sprint Planning: During Sprint Planning, the Developers collaboratively select Product Backlog items they will work on to achieve the Sprint Goal. They assess their capacity, the complexity of tasks, and dependencies among tasks to make informed decisions.
- During the Sprint: As the Sprint progresses, Developers continue to select tasks from the Sprint Backlog based on the flow of work and team capacity. This autonomy allows them to adapt quickly to changes, such as unanticipated challenges or new insights.
Example 2: The Developers Make Decisions on How to Achieve the Sprint Goal
Self-managing Scrum Teams are responsible for determining how to accomplish their work:
- Problem-Solving: Developers engage in problem-solving without needing external direction. When faced with obstacles or technical challenges, they collaboratively discuss potential solutions and decide on the best course of action.
- Adapting Work Processes: If the team finds that a certain approach is not working effectively, they have the autonomy to adapt their work processes. For example, they might decide to switch to a different tool, adjust their workflow, or redistribute tasks among team members to better align with the Sprint Goal.
Relevance to the PSM III Exam
The PSM III exam requires a deep understanding of Scrum principles, including self-management. Knowing the specific behaviors that demonstrate self-management helps in recognizing and fostering these traits within Scrum Teams, ensuring they can deliver value effectively and adapt to change.
Key Takeaways
- Self-managing teams are autonomous in selecting and managing their work throughout the Sprint.
- Developers make decisions on how to achieve the Sprint Goal without needing external direction.
- Autonomy fosters adaptability, enabling teams to respond to challenges and changes efficiently.
Conclusion
Self-management is a cornerstone of Scrum that enables teams to be flexible, responsive, and efficient. By empowering Developers to select their own work and make decisions on how to achieve their goals, Scrum Teams can better navigate the complexities of product development.

Get ready for the official PSM III exam
80+ PSM III essay practice questions, each with a model answer and an in-depth explanation.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 24 random questions in 150 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM III exam fee ($500) is paid separately to Scrum.org.
More PSM III exam questions
- Scrum has no explicit artifacts for the product vision and a Sprint Goal. Yet, they are important. How would you explain their importance?
- A valuable and useful product Increment needs to represent the product’s non-functional requirements; such as, stability, security, financial integrity, performance, reliability, extensibility, marketability, and other requirements.
- Scrum Teams often use velocity as a technique to measure historical output.
- Many products and systems have complex architectures and operate on sophisticated infrastructures.
- A new Scrum Team wonders whether validation of quality should be done within every Sprint.” (PSM III)