Answering: “At Sprint Planning, the Scrum Team has NO clear standard to meet for releasable software. What should the Scrum Team do?”

Addressing the Lack of a Definition of Done in Sprint Planning

The Definition of Done (DoD) is a crucial aspect of Scrum, ensuring that all Scrum Team members have a shared understanding of what it means for work to be complete and potentially releasable. When a Scrum Team does not have a clear standard for releasable software during Sprint Planning, they need to establish a Definition of Done to guide their work.

Exam Question

At Sprint Planning, the Scrum Team has NO clear standard to meet for releasable software. What should the Scrum Team do?
(choose the best answer)
A. Specify a Definition of Done.
B. Ask the Scrum Master what they should do.
C. Create a unique completion checklist for each item in the Sprint.
D. Ask the Product Owner to specify a Definition of Done.

Correct Answer

A. Specify a Definition of Done.

Explanation

Correct Answer

A. Specify a Definition of Done:
The Definition of Done is a critical component of Scrum that defines the criteria for when a Product Backlog item or Increment is considered complete. If the Scrum Team does not have a clear standard for what constitutes releasable software, it is imperative that they specify a Definition of Done. This ensures that everyone on the team shares a common understanding of what it means to complete work to a releasable standard, thereby avoiding ambiguity and ensuring quality.

Why the Other Options Are Less Appropriate

B. Ask the Scrum Master what they should do:
While the Scrum Master can facilitate discussions and guide the team, it is not their responsibility to dictate what the Definition of Done should be. The Scrum Team, including the Developers and Product Owner, must collaboratively decide on the Definition of Done.

C. Create a unique completion checklist for each item in the Sprint:
Creating a unique checklist for each item can lead to inconsistencies and confusion about what is considered done. A standard Definition of Done provides a consistent, clear, and agreed-upon set of criteria that applies to all work items, promoting alignment and quality.

D. Ask the Product Owner to specify a Definition of Done:
While the Product Owner has a stake in the Definition of Done, it should not be created by the Product Owner alone. The entire Scrum Team should be involved in defining it, ensuring that it reflects both the technical and business perspectives.

Relevance to the PSD Exam

Understanding the importance of the Definition of Done and how to establish it during Sprint Planning is crucial for the PSD exam. It ensures that all team members are aligned on what constitutes completion, leading to higher-quality deliverables.

Key Takeaways

  • Definition of Done is essential for ensuring that all work meets a shared standard of quality and completeness.
  • The Scrum Team should collaboratively specify the Definition of Done if it is not already established.
  • A consistent Definition of Done helps prevent ambiguity and confusion and promotes the delivery of high-quality, potentially releasable software.

Conclusion

When the Scrum Team lacks a clear standard for releasable software during Sprint Planning, they should specify a Definition of Done to ensure that all work meets an agreed-upon level of quality and completeness. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSD I Exam on the First Try
ScrumPrep

PSD Exam Guide

The Professional Scrum Developer (PSD) exam is an essential certification for anyone interested in developing valuable software using the Scrum framework. The PSD certification is proof of one’s understanding of the principles, practices, and techniques of developing products using Scrum. Passing this exam requires adequate preparation, practice, and dedication. In this article, we will discuss various tips and techniques to help you pass the PSD exam on your first attempt. Table of Contents Understanding the PSD Exam Before diving into the preparation strategies, it’s essential to understand the exam format and content. The PSD exam is a multiple-choice test that consists of 80 questions, and you have 60 minutes to complete it. The questions are designed to test your knowledge

Read More »

Related Products

LIMITED TIME SALE!
PSD Practice Tests - ScrumPrep
Pass the PSD exam with ease using our comprehensive practice exams. Boost your skills in modern engineering practices and become a certified Scrum Developer.
  • 127 PSDâ„¢ exam sample questions
  • Six complete exams with 20 to 27 questions each
  • Real exam mode with unlimited question combinations​
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSDâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here