A Product Backlog is an inventory of what the product needs, ordered by factors such as value, dependencies and risk, and managed by the Product Owner. It is not a fixed, pre-approved requirements list and it is not hidden from the team.
Exam Question
A Product Backlog is: (choose the best three answers)
- A. An inventory of things to be done for the Product.
- B. Ordered based on priority, value, dependencies, and risk.
- C. An exhaustive list of upfront approved requirements to be implemented.
- D. Managed by the Product Owner.
- E. Only visible to the Product Owner and stakeholders.
Correct Answer
A, B and D.
Why This Is the Correct Answer
The Scrum Guide describes the Product Backlog as “an emergent, ordered list of what is needed to improve the product.” That makes it an inventory of things to be done, and it is ordered. Value, dependencies and risk are typical factors in that order. The Product Owner is accountable for managing it, including “ordering Product Backlog items” and “ensuring that the Product Backlog is transparent, visible and understood.” Because it is emergent, it changes as the team and stakeholders learn, which rules out an upfront approved list.
Why the Other Options Are Wrong
C. An exhaustive list of upfront approved requirements. The Product Backlog is emergent and never complete. Freezing it up front contradicts empiricism.
E. Only visible to the Product Owner and stakeholders. The Product Backlog must be transparent and visible, including to the Developers who pull work from it.
Exam Tip
If an option calls the Product Backlog complete, exhaustive, approved or baselined, it is wrong. Scrum’s Product Backlog is emergent and transparent.
Key Takeaways
- The Product Backlog is an emergent, ordered list of product needs.
- The Product Owner is accountable for managing it.
- Everyone, including the Developers, can see it.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Scrum requires that the Product Owner must use which of the following items?” (PSM I)
- What factor should be considered when establishing the Sprint length?
- Who determines how many Product Backlog items the Developers select for a Sprint?” (PSM I)
- If burndown charts are used to visualize progress, what do they track?” (PSM I)
- What are two ways that regulatory compliance issues are dealt with in Scrum?” (PSM I)