Hypothesis Testing in Scrum: Experimentation with Product Backlog Items
Hypothesis testing via experimentation is a key practice in Scrum, allowing teams to validate assumptions and make informed decisions about product development. Understanding which types of Product Backlog Items (PBIs) are most suited for this process is crucial for effective backlog management.
Exam Question
Which of the following Product Backlog Item types are most suited for hypothesis testing via experimentation?
(choose the best answer)
A. Low value, High risk.
B. High value, High risk.
C. Low value, Low risk.
D. High value, Low risk.
Correct Answer
B. High value, High risk.
Explanation
Correct Answer
B. High value, High risk:
PBIs that are both high value and high risk are the most suited for hypothesis testing via experimentation. These items are critical because they offer significant value to the product but come with considerable uncertainty. Experimentation helps in validating whether the high-risk elements can deliver the expected high value, thereby reducing uncertainty and potential negative impact on the project.
Why the Other Options Are Less Effective
A. Low value, High risk:
Investing time and resources in experimenting with low-value, high-risk items is generally not advisable. The potential return does not justify the risk involved, making it less efficient to focus on these items.
C. Low value, Low risk:
Low-value, low-risk items do not significantly impact the product’s success, making them less important for hypothesis testing. These items can be addressed with straightforward implementation rather than experimentation.
D. High value, Low risk:
While high-value, low-risk items are important, they do not require experimentation for validation as their risk is already low. These items can typically be implemented directly with confidence in their expected outcomes.
Benefits of Hypothesis Testing for High Value, High Risk PBIs
- Risk Mitigation: Experimentation helps in identifying and mitigating risks associated with high-value items.
- Informed Decision Making: Validating assumptions through testing provides data-driven insights for better decision-making.
- Optimized Resource Allocation: Focusing on high-value, high-risk items ensures that resources are used effectively to address the most critical uncertainties.
Relevance to the PSU I Exam
Understanding which PBIs are best suited for hypothesis testing is essential for the PSU I exam. It demonstrates the ability to apply experimental techniques to manage uncertainty and validate assumptions, which are critical skills for integrating UX practices into Scrum.
Key Takeaways
- High-value, high-risk PBIs are most suited for hypothesis testing via experimentation.
- Experimentation helps in validating critical assumptions and mitigating risks.
- Effective hypothesis testing leads to better-informed decisions and optimized resource use.
Conclusion
In Scrum, focusing on hypothesis testing for high-value, high-risk PBIs is a strategic approach to manage uncertainty and validate critical assumptions. This practice ensures that the team can make informed decisions and deliver maximum value.

Get ready for the official PSU I exam
80 PSU I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 60 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSU I exam fee ($200) is paid separately to Scrum.org.
More PSU I exam questions
- The best way to manage design work that lasts more than one Sprint is:
- True or False: UX activities should be managed in a Discovery Backlog.
- Which best describes the benefits of using UX practices on a Scrum Team?
- True or False: Every experiment should identify the criteria by which its success or failure will be evaluated.
- True or False: A hypothesis statement could be used to express a Product Backlog item when you want to explicitly define the outcome or business value.
